Land east of Kingsley Sports Club (5 MW solar)

Land east of Kingsley Sports Club is a 5 MW solar project in East Hampshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 30 April 2017; the record was last updated on 19 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar
permission expiredstatus in REPD
19 July 2017record last updated
East Hampshirecouncil area

Planning timeline

DateStage
29 January 2014Application submitted
30 April 2014Planning permission granted
30 April 2017Permission expired

Project details

Technology
solar
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
19 July 2017
Operator or applicant
Granite Solar
Planning authority
East Hampshire
Planning application reference
52947/002
Address (REPD)
Sickles Lane, Kingsley, Alton
Council area (by location)
East Hampshire
Time to decision
13 weeks
REPD reference
2374

Earlier applications for this site

ApplicationMWSubmittedOutcome
Land east of Kingsley Sports Club 52947/00158 November 2012withdrawn 7 February 2013

Who decides

ApplicationsEast HampshireUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused2 of 1612%
Battery storage refused2 of 316%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land to the north and south of Cakers Lane (Wilsom)solar farm11operational5.7
Wilsom Farmsolar farm11operational5.7
Copse Close Solar Farmsolar farm49.9approved, not built6.7
Marsh House Solar Parksolar farm5.5operational7.4
Barley Wood Farm Lanesolar farm5.4operational8.2
Gaston Lane, Farringdon Solar Farm & Battery Storagesolar farm44application submitted8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1401, -0.868).