Energy Projects Near You

Solar, wind and battery projects near Liss (GU33)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GU33 (East Hampshire): 2 are waiting for a planning decision, 5 approved but not yet running, 2 operational. The largest live scheme is Copse Close Solar Farm (49.9 MW solar farm, approved on 6 February 2023, not yet built; REPD status may be out of date), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
2awaiting a decision
5approved, not running
2operational

Projects within 10 km of GU33

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Whitman Laboratoriesrooftop solarrooftop solar1operationalupdated Oct 2017Jun 2016granted Aug 2016Oct 2017East Hampshire6.6
Barley Wood Farm Lanesolar farmsolar farm5.4operationalupdated May 2015Dec 2013granted Mar 2014May 2015East Hampshire9.3
Gaston Lane, Farringdon Solar Farm & Battery Storagesolar farmsolar farm44application submittedupdated Aug 2025Jun 2025—Aug 2025East Hampshire9.4
Gaston Lane, Farringdon Solar Farm & Battery Storagebattery storagebattery storage2application submittedupdated Aug 2025Jun 2025—Aug 2025East Hampshire9.4
Copse Close Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2023Mar 2022granted Feb 2023Feb 2023East Hampshire9.9
Land east of Kingsley Sports Clubsolarsolar5permission expiredupdated Jul 2017Jan 2014granted Apr 2014Jul 2017East Hampshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Old Thorns Golf and Country Clubrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Feb 2023granted Mar 2023Mar 2023East Hampshire4.8
Reeves Britannia, The Causewayrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025East Hampshire7.0
The New Barn, Bedford Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2022Oct 2022granted Dec 2022Dec 2022East Hampshire7.0
Copse Close Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Apr 2022Mar 2022granted Feb 2023Apr 2022East Hampshire9.9

Distance from the average position of the GU33 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3111093.9
Rooftop solar403100.6
Solar100000
Battery storage211002

MW in pipeline: pending, approved and under-construction capacity.

How East Hampshire decides solar, wind and battery applications

ApplicationsEast HampshireUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused2 of 1612%
Battery storage refused2 of 316%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in East Hampshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GU33, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.