Energy Projects Near You

Solar, wind and battery projects near Liphook (GU30)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GU30 (East Hampshire): 1 is waiting for a planning decision, 2 approved but not yet running. The largest live scheme is Sandhill Farm, Picketts Hill (0.4 MW rooftop solar, approved on 2 October 2024, not yet built), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
1awaiting a decision
2approved, not running
0operational

Projects within 10 km of GU30

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land east of Kingsley Sports Clubsolarsolar5permission expiredupdated Jul 2017Jan 2014granted Apr 2014Jul 2017East Hampshire8.4
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Old Thorns Golf and Country Clubrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Feb 2023granted Mar 2023Mar 2023East Hampshire2.0
Tilford Road, Nr Tower Road - Micro Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated Sep 2024Aug 2024—Sep 2024Waverley6.8
Sandhill Farm, Picketts Hillrooftop solarrooftop solar0.4approved, not builtupdated Oct 2024Oct 2022granted Oct 2024Oct 2024East Hampshire7.9

Distance from the average position of the GU30 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar202000.7
Solar100000
Battery storage110000.2

MW in pipeline: pending, approved and under-construction capacity.

How East Hampshire decides solar, wind and battery applications

ApplicationsEast HampshireUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused2 of 1612%
Battery storage refused2 of 316%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in East Hampshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GU30, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.