Energy Projects Near You

Barley Wood Farm Lane (5.4 MW solar farm)

Barley Wood Farm Lane is a 5.4 MW solar farm project in East Hampshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 March 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.4 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
East Hampshirecouncil area

Planning timeline

DateStage
9 December 2013Application submitted
31 March 2014Planning permission granted
1 January 2015Construction started
20 March 2015Operational

Project details

Technology
solar farm
Capacity
5.4 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
East Hampshire
Planning application reference
54507/002
Site area
14.9 ha
Address (REPD)
Land South of, Gaston Lane, Farringdon, Alton
Council area (by location)
East Hampshire
Time to decision
16 weeks
REPD reference
1474

Earlier applications for this site

ApplicationMWSubmittedOutcome
Gaston Lane 54507/0015.811 June 2013withdrawn 14 August 2013

Who decides

ApplicationsEast HampshireUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused2 of 1612%
Battery storage refused2 of 316%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gaston Lane, Farringdon Solar Farm & Battery Storagesolar farm44application submitted0.2
Copse Close Solar Farmsolar farm49.9approved, not built1.9
Wilsom Farmsolar farm11operational3.7
Land to the north and south of Cakers Lane (Wilsom)solar farm11operational3.7
Land east of Kingsley Sports Clubsolar5permission expired8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1147, -0.9782).