Energy Projects Near You

Wilsom Farm (11 MW solar farm)

Wilsom Farm is an 11 MW solar farm project in East Hampshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 28 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWsolar farm
operationalstatus in REPD
28 July 2016record last updated
East Hampshirecouncil area

Planning timeline

DateStage
20 January 2015Application submitted
2 November 2015Planning permission granted
21 December 2015Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
11 MW
Status (REPD)
operational
Record last updated
28 July 2016
Operator or applicant
Canadian solar
Planning authority
East Hampshire
Planning application reference
55465/001
Site area
22.2 ha
Address (REPD)
Cakers Lane, East Worldham, Alton, Hampshire
Council area (by location)
East Hampshire
Time to decision
41 weeks
REPD reference
1515

Who decides

ApplicationsEast HampshireUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused2 of 1612%
Battery storage refused2 of 316%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land to the north and south of Cakers Lane (Wilsom)solar farm11operational<0.1
Copse Close Solar Farmsolar farm49.9approved, not built1.8
Barley Wood Farm Lanesolar farm5.4operational3.7
Gaston Lane, Farringdon Solar Farm & Battery Storagesolar farm44application submitted3.8
Land east of Kingsley Sports Clubsolar5permission expired5.7
Fleet Hill Solar Farmsolar farm47.5under construction9.0
Marsh House Solar Parksolar farm5.5operational10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1424, -0.9501).