Energy Projects Near You

Solar, wind and battery projects near Petersfield (GU32)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GU32 (East Hampshire): 3 approved but not yet running, 1 operational. The largest live scheme is The New Barn, Bedford Road (0.2 MW rooftop solar, approved on 2 December 2022, not yet built; REPD status may be out of date), 1.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
3approved, not running
1operational

Projects within 10 km of GU32

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Whitman Laboratoriesrooftop solarrooftop solar1operationalupdated Oct 2017Jun 2016granted Aug 2016Oct 2017East Hampshire1.3
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The New Barn, Bedford Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2022Oct 2022granted Dec 2022Dec 2022East Hampshire1.5
Reeves Britannia, The Causewayrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025East Hampshire2.4
Whitewool Farm, East Meonrooftop solarrooftop solar0.2approved, not builtupdated May 2024Mar 2024granted May 2024May 2024East Hampshire7.4

Distance from the average position of the GU32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar403100.5

MW in pipeline: pending, approved and under-construction capacity.

How East Hampshire decides solar, wind and battery applications

ApplicationsEast HampshireUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused2 of 1612%
Battery storage refused2 of 316%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in East Hampshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GU32, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.