Saxley Farm (5 MW solar farm)
Saxley Farm is a 5 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 30 April 2014.
5 MWsolar farm
operationalstatus in REPD
30 April 2014record last updated
Test Valleycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 27 September 2013 | Application submitted |
| 18 December 2013 | Planning permission granted |
| 31 March 2014 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- operational
- Record last updated
- 30 April 2014
- Operator or applicant
- Solar Century/ Bluefield Solar
- Planning authority
- Test Valley
- Planning application reference
- 13/02122/FULLN
- Address (REPD)
- Saxley Farm Saxley Farm Lane Red Rice Andover Hampshire SP11 7PG
- Council area (by location)
- Test Valley
- Time to decision
- 12 weeks
- REPD reference
- 1333
Who decides
| Applications | Test Valley | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 7 of 41 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 1 of 7 | 16% |
| Median time from submission to decision | 23.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Abbots Ann | solar farm | 7 | operational | 1.7 |
| Westover Farm | solar farm | 7 | operational | 2.1 |
| Winchester Road, Wherwell Solar Farm | solar farm | 45.9 | approved, not built | 5.3 |
| Andover Solar Farm | solar farm | 5 | operational | 5.6 |
| Solar Farm at Gander Down Solar Farm | solar farm | 6.2 | approved, not built | 5.7 |
| Eveley Farm | solar farm | 49 | operational | 6.0 |
| Cowdown Lane | solar farm | 40 | operational | 6.6 |
| Cholderton Road, Quarley Solar Farm | solar farm | 22.5 | approved, not built | 6.7 |
| Lains Farm | solar farm | 5 | operational | 6.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.161, -1.5363).