Eveley Farm (49 MW solar farm)

Eveley Farm is a 49 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 March 2016; the record was last updated on 23 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWsolar farm
operationalstatus in REPD
23 March 2016record last updated
Test Valleycouncil area

Planning timeline

DateStage
16 February 2015Application submitted
27 July 2015Planning permission granted
1 March 2016Construction started
17 March 2016Operational

Project details

Technology
solar farm
Capacity
49 MW
Status (REPD)
operational
Record last updated
23 March 2016
Operator or applicant
PS Renewables
Planning authority
Test Valley
Planning application reference
15/00094/FULLS
Site area
77.6 ha
Address (REPD)
Land At Eveley Farm Stevens Drove Houghton Stockbridge
Council area (by location)
Test Valley
Time to decision
23 weeks
REPD reference
5080

Earlier applications for this site

ApplicationMWSubmittedOutcome
Eveley Farm 13/02735/FULLS4911 December 2013refused 15 August 2014

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm at Gander Down Solar Farmsolar farm6.2approved, not built0.2
Somborne Park Roadsolar farm5refused3.7
Saxley Farmsolar farm5operational6.0
Westover Farmsolar farm7operational6.3
Abbots Annsolar farm7operational6.4
Winchester Road, Wherwell Solar Farmsolar farm45.9approved, not built9.0