Energy Projects Near You

Hatherden Farm (49.9 MW solar farm)

Hatherden Farm is a 49.9 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2025; the record was last updated on 11 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
operationalstatus in REPD
11 November 2025record last updated
Test Valleycouncil area

Planning timeline

DateStage
20 December 2019Application submitted
5 June 2020Planning permission granted
1 August 2022Construction started
1 October 2025Operational

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
11 November 2025
Operator or applicant
Nextpower SPV 10 Limited
Planning authority
Test Valley
Planning application reference
19/03043/FULLN
Site area
80.0 ha
Address (REPD)
Hatherden Farm, Hatherden Lane, Hatherden, Andover, Hampshire
Council area (by location)
Test Valley
Time to decision
24 weeks
Contracts for Difference
AR4
REPD reference
7425

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Andover Solar Farmsolar farm5operational4.5
South Way, Walworth Business Park Solar Photovoltaicsrooftop solar5.2application withdrawn5.5
South Park Solar Farmsolar farm15approved, not built6.1
Lower Wyke Farm, St Mary Bourne Solar Farmsolar farm21approved, not built6.7
Cowdown Lanesolar farm40operational6.8
Perham Down - Meadow Solar Farm & Battery Storagesolar farm49.9approved, not built8.0
Winchester Road, Wherwell Solar Farmsolar farm45.9approved, not built8.6
Cholderton Road, Quarley Solar Farmsolar farm22.5approved, not built8.8
Lains Farmsolar farm5operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2483, -1.5102).