Energy Projects Near You

Perham Down - Meadow Solar Farm & Battery Storage (49.9 MW)

Perham Down - Meadow Solar Farm & Battery Storage is a 49.9 MW solar farm project in Test Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 November 2022, not yet built; the record was last updated on 9 December 2022. REPD also records that the planning permission expired on 18 November 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
9 December 2022record last updated
Test Valleycouncil area

REPD also records that the planning permission expired on 18 November 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
9 June 2021Application submitted
18 November 2022Planning permission granted
18 November 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
9 December 2022
Operator or applicant
Low Carbon UK Solar Investment Co Limited
Planning authority
Test Valley
Planning application reference
21/01749/FULLN
Site area
75.5 ha
Address (REPD)
Meadow Solar Farm, Se/O Perham Down, Andover
Council area (by location)
Test Valley
Time to decision
75 weeks
REPD reference
9175

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsTest ValleyUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused7 of 4112%
Onshore wind refused0 of 145%
Battery storage refused1 of 716%
Median time from submission to decision23.6 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Farm (Thruxton)solar farm12.5application withdrawn2.1
South Park Solar Farmsolar farm15approved, not built2.5
Cholderton Road, Quarley Solar Farmsolar farm22.5approved, not built2.9
Lains Farmsolar farm5operational3.0
Shipton Bellinger - Park House Corner Solar Farmsolar farm5.4operational4.7
Parkhouse Corner (Orta Solar)solar farm6.6operational5.1
Down Barn Farmsolar farm49.9approved, not built5.8
Andover Solar Farmsolar farm5operational5.9
Hatherden Farmsolar farm49.9operational8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2251, -1.6189).