Energy Projects Near You

Solar, wind and battery projects near Warminster (BA12)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BA12 (Wiltshire): 1 is waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Lodge Hill, Berkley Solar Park (14.5 MW solar farm, approved on 21 October 2022, not yet built), 8.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
1awaiting a decision
2approved, not running
1operational

Projects within 10 km of BA12

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Summerslade Down Wind Clusterwind farmwind farm2.2refusedupdated Oct 2011Oct 1998refused May 1999Oct 2011Wiltshire3.5
Chicklade EV Service Station Solar Farmsolar farmsolar farm3application submittedupdated Mar 2026Feb 2026—Mar 2026Wiltshire7.9
Lodge Hill, Berkley Solar Parksolar farmsolar farm14.5approved, not builtupdated Feb 2026Nov 2021granted Oct 2022Feb 2026Somerset8.8
Court Farm (Frome)solar farmsolar farm6.8refused on appealupdated Sep 2014May 2014refused Aug 2014Sep 2014Somerset9.4
West Woodlandssolar farmsolar farm5operationalupdated Apr 2016Nov 2014granted Aug 2015Apr 2016Somerset9.4
Selwood Solar Farmsolar farmsolar farm6application withdrawnupdated Nov 2021Oct 2021—Nov 2021Somerset9.9
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Morrisons, Weymouth Streetrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Oct 2022granted Dec 2022Jan 2023Wiltshire3.7

Distance from the average position of the BA12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5111117.5
Rooftop solar101000.2
Wind farm100010

MW in pipeline: pending, approved and under-construction capacity.

How Wiltshire decides solar, wind and battery applications

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

All projects in Wiltshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.