Braydon Manor Farm (8.7 MW solar farm)

Braydon Manor Farm is an 8.7 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 January 2016; the record was last updated on 18 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.7 MWsolar farm
operationalstatus in REPD
18 July 2016record last updated
Wiltshirecouncil area

Planning timeline

DateStage
12 June 2013Application submitted
29 October 2013Planning permission granted
24 September 2015Construction started
15 January 2016Operational

Project details

Technology
solar farm
Capacity
8.7 MW
Status (REPD)
operational
Record last updated
18 July 2016
Operator or applicant
Public Power Solutions
Planning authority
Wiltshire
Planning application reference
13/01723/FUL
Address (REPD)
Braydon Manor Farm, Braydon
Council area (by location)
Wiltshire
Time to decision
20 weeks
REPD reference
1974

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ravensroost Farm, Minetybattery storage49.9approved, not built1.7
Bentham Farmsolar farm8operational3.2
Somerford Farm, Brinkworthbattery storage6.6approved, not built3.6
Fairholme, Minetybattery storage50approved, not built3.8
Park Grounds Farmsolar farm5abandoned3.8
Minety Northbattery storage50abandoned3.9
Minety Southbattery storage50operational3.9
Mopes Lane, Purton Solar Farmsolar farm20approved, not built4.4
Minety South 2battery storage50operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5885, -1.9362).