Energy Projects Near You

Park Grounds Farm (5 MW solar farm)

Park Grounds Farm is a 5 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 26 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
26 April 2017record last updated
Wiltshirecouncil area

Planning timeline

DateStage
11 August 2015Application submitted
10 December 2015Planning permission granted
10 December 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
26 April 2017
Operator or applicant
Earthworm Energy
Planning authority
Wiltshire
Planning application reference
15/07373/FUL
Site area
11.6 ha
Address (REPD)
Park Grounds, Brinkworth Road, Royal Wootton Bassett, Swindon
Council area (by location)
Wiltshire
Time to decision
17 weeks
REPD reference
5585

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Spittleborough Farmsolar farm12operational3.3
Braydon Manor Farmsolar farm8.7operational3.8
Wickfield Farmsolar farm5operational4.2
Ravensroost Farm, Minetybattery storage49.9approved, not built4.9
Park Farmbattery storage10permission expired5.0
Rock Farm / Goldborough Farm (Rookwood)solar farm5operational5.1
Somerford Farm, Brinkworthbattery storage6.6approved, not built5.4
Bentham Farmsolar farm8operational6.0
Mopes Lane, Purton Solar Farmsolar farm20approved, not built6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5547, -1.9276).