Spittleborough Farm (12 MW solar farm)

Spittleborough Farm is a 12 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 March 2014; the record was last updated on 26 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
26 August 2014record last updated
Wiltshirecouncil area

Planning timeline

DateStage
15 July 2013Application submitted
9 December 2013Planning permission granted
31 January 2014Construction started
25 March 2014Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
26 August 2014
Operator or applicant
MTS Spittleborough Solar Ltd
Planning authority
Wiltshire
Planning application reference
13/02191/FUL
Site area
22.7 ha
Address (REPD)
Swindon Road Lydiard Tregoze Royal Wootton Bassett Wiltshire
Council area (by location)
Wiltshire
Time to decision
21 weeks
REPD reference
2061

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wickfield Farmsolar farm5operational0.9
Park Farmbattery storage10permission expired2.1
Rock Farm / Goldborough Farm (Rookwood)solar farm5operational3.0
Park Grounds Farmsolar farm5abandoned3.3
Mannington Battery Storage Plantbattery storage49.9operational4.7
Brindley Close (Extension)battery storage6under construction5.5
Mopes Lane, Purton Solar Farmsolar farm20approved, not built5.7
Braydon Manor Farmsolar farm8.7operational6.0
Bentham House Farm, Mopes Lane Solar Farmsolar farm12approved, not built6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5464, -1.8814).