Wickfield Farm (5 MW solar farm)

Wickfield Farm is a 5 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 21 March 2017; the record was last updated on 4 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 July 2017record last updated
Wiltshirecouncil area

Planning timeline

DateStage
6 March 2014Application submitted
5 June 2014Planning permission granted
2 January 2017Construction started
21 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 July 2017
Operator or applicant
NESF (formerly A C Crocker Properties Ltd)
Planning authority
Wiltshire
Planning application reference
14/02508/FUL
Site area
10.8 ha
Address (REPD)
Wickfield Farm Royal Wootton Bassett Swindon
Council area (by location)
Wiltshire
Time to decision
13 weeks
REPD reference
1784

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Spittleborough Farmsolar farm12operational0.9
Park Farmbattery storage10permission expired1.9
Rock Farm / Goldborough Farm (Rookwood)solar farm5operational2.5
Mannington Battery Storage Plantbattery storage49.9operational4.1
Park Grounds Farmsolar farm5abandoned4.2
Brindley Close (Extension)battery storage6under construction5.3
Wroughton Airfield Solar Parksolar farm41operational5.3
Lower Basset Down Farmsolar farm10.5operational5.8
Mopes Lane, Purton Solar Farmsolar farm20approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5415, -1.8708).