Lower Basset Down Farm (10.5 MW solar farm)

Lower Basset Down Farm is a 10.5 MW solar farm project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 March 2016; the record was last updated on 22 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.5 MWsolar farm
operationalstatus in REPD
22 March 2016record last updated
Swindoncouncil area

Planning timeline

DateStage
20 June 2014Application submitted
3 December 2014Planning permission granted
20 November 2015Construction started
18 March 2016Operational

Project details

Technology
solar farm
Capacity
10.5 MW
Status (REPD)
operational
Record last updated
22 March 2016
Operator or applicant
INRG Solar
Planning authority
Swindon
Planning application reference
S/14/0899
Site area
16.6 ha
Address (REPD)
Land At Lower Basset Down Farm Hay Lane Bassett Down Swindon
Council area (by location)
Swindon
Time to decision
24 weeks
REPD reference
1850

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wroughton Airfield Solar Parksolar farm41operational2.1
Mannington Battery Storage Plantbattery storage49.9operational3.6
Park Farmbattery storage10permission expired5.6
Brindley Close (Extension)battery storage6under construction5.8
Wickfield Farmsolar farm5operational5.8
Rock Farm / Goldborough Farm (Rookwood)solar farm5operational6.2
Spittleborough Farmsolar farm12operational6.7
Honda wind Farmwind farm6.9refused8.2
Mount Pleasant Farm Solar Farmsolar farm35application submitted8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5245, -1.7914).