Brindley Close (Extension) (6 MW battery storage)

Brindley Close (Extension) is a 6 MW battery storage project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 May 2022; the record was last updated on 25 January 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWbattery storage
under constructionstatus in REPD
25 January 2023record last updated
Swindoncouncil area

Planning timeline

DateStage
13 July 2020Application submitted
4 September 2020Planning permission granted
1 May 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
6 MW
Status (REPD)
under construction
Record last updated
25 January 2023
Operator or applicant
Public Power Solutions
Planning authority
Swindon
Planning application reference
S/20/0850
Address (REPD)
Land At, Brindley Close, Cheney Manor Industrial Estate, Swindon,
Council area (by location)
Swindon
Time to decision
8 weeks
REPD reference
8045

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mannington Battery Storage Plantbattery storage49.9operational2.3
Park Farmbattery storage10permission expired3.4
Chapel Farmsolar farm5operational4.3
Bentham House Farm, Mopes Lane Solar Farmsolar farm12approved, not built4.6
Mopes Lane, Purton Solar Farmsolar farm20approved, not built4.9
Wickfield Farmsolar farm5operational5.3
Catsbrain Farmbattery storage30approved, not built5.5
Spittleborough Farmsolar farm12operational5.5
Little Rose Lane, Blunsdonsolar farm15approved, not built5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5742, -1.8152).