Energy Projects Near You

Mopes Lane, Purton Solar Farm (20 MW)

Mopes Lane, Purton Solar Farm is a 20 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 April 2023, not yet built; the record was last updated on 8 December 2021. REPD records the planning permission as expiring on 15 April 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtmay be out of datestatus in REPD
8 December 2021record last updated
Wiltshirecouncil area

REPD records the planning permission as expiring on 15 April 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
3 November 2021Application submitted
15 April 2023Planning permission granted
15 April 2026Permission expired

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
8 December 2021
Operator or applicant
Spring Dev 08 Limited
Planning authority
Wiltshire
Planning application reference
PL/2021/10405
Site area
23.7 ha
Address (REPD)
Hills Minerals & Waste Ltd, Mopes Lane, Purton,
Council area (by location)
Wiltshire
Time to decision
75 weeks
Contracts for Difference
AR5
Name in REPD
Mopes Lane, Purton - Solar Farm
REPD reference
9849

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bentham House Farm, Mopes Lane Solar Farmsolar farm12approved, not built0.7
Bentham Farmsolar farm8operational1.9
Chapel Farmsolar farm5operational4.3
Braydon Manor Farmsolar farm8.7operational4.4
Malmesbury Road Solar Farmsolar farm13approved, not built4.6
Park Farmbattery storage10permission expired4.9
Brindley Close (Extension)battery storage6under construction4.9
Spittleborough Farmsolar farm12operational5.7
Ravensroost Farm, Minetybattery storage49.9approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5977, -1.8746).