Mannington Battery Storage Plant (49.9 MW)

Mannington Battery Storage Plant is a 49.9 MW battery storage project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2021; the record was last updated on 14 September 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
operationalstatus in REPD
14 September 2022record last updated
Swindoncouncil area

Planning timeline

DateStage
21 November 2017Application submitted
7 December 2018Planning permission granted
1 November 2020Construction started
1 October 2021Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
14 September 2022
Operator or applicant
Still Waters Green Technology
Planning authority
Swindon
Planning application reference
S/17/1879
Address (REPD)
Mannington Depot Telford Way, Service Road, Mannington, Swindon, Wiltshire
Council area (by location)
Swindon
Time to decision
54 weeks
REPD reference
7024

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brindley Close (Extension)battery storage6under construction2.3
Park Farmbattery storage10permission expired2.8
Lower Basset Down Farmsolar farm10.5operational3.6
Wickfield Farmsolar farm5operational4.1
Spittleborough Farmsolar farm12operational4.7
Wroughton Airfield Solar Parksolar farm41operational4.8
Rock Farm / Goldborough Farm (Rookwood)solar farm5operational5.9
Bentham House Farm, Mopes Lane Solar Farmsolar farm12approved, not built6.3
Mopes Lane, Purton Solar Farmsolar farm20approved, not built6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5535, -1.815).