Energy Projects Near You

Wroughton Airfield Solar Park (41 MW)

Wroughton Airfield Solar Park is a 41 MW solar farm project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 31 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41 MWsolar farm
operationalstatus in REPD
31 July 2017record last updated
Swindoncouncil area

Planning timeline

DateStage
15 July 2013Application submitted
2 April 2014Secretary of State intervened
19 March 2015Secretary of State granted
11 February 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
41 MW
Status (REPD)
operational
Record last updated
31 July 2017
Operator or applicant
Rockfire Capital
Planning authority
Swindon
Planning application reference
S/13/0809
Site area
67.0 ha
Address (REPD)
Land At Science Museum, Orbital Road, Wroughton, Swindon
Council area (by location)
Swindon
REPD reference
1735

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lower Basset Down Farmsolar farm10.5operational2.1
Mannington Battery Storage Plantbattery storage49.9operational4.8
Rock Farm / Goldborough Farm (Rookwood)solar farm5operational4.8
Wickfield Farmsolar farm5operational5.3
Park Farmbattery storage10permission expired5.8
Spittleborough Farmsolar farm12operational6.2
Brindley Close (Extension)battery storage6under construction7.1
Park Grounds Farmsolar farm5abandoned9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5104, -1.8124).