Catsbrain Farm (30 MW battery storage)

Catsbrain Farm is a 30 MW battery storage project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 October 2023, not yet built; the record was last updated on 4 August 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtstatus in REPD
4 August 2022record last updated
Swindoncouncil area

Planning timeline

DateStage
11 July 2022Application submitted
3 October 2023Planning permission granted
3 October 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
4 August 2022
Operator or applicant
Conrad Energy (Developments) II Limited
Planning authority
Swindon
Planning application reference
S/22/1051
Address (REPD)
N/O Kingsdown Road & West Of Catsbrain Farm Swindon
Council area (by location)
Swindon
Time to decision
64 weeks
Name in REPD
Catsbrain Farm - Battery Storage
REPD reference
11787

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Queenslaine Farm, Highworth Roadbattery storage66approved, not built1.3
Honda wind Farmwind farm6.9refused1.7
Corner Copse Solar Farmsolar farm49.9under construction1.7
Stanton solar parksolar farm5operational1.9
Sevor Farmsolar farm9.3operational2.4
Roves Farm (Solar)solar farm12.7operational3.5
Little Rose Lane, Blunsdonsolar farm15approved, not built4.2
Chapel Farmsolar farm5operational4.9
Brindley Close (Extension)battery storage6under construction5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6008, -1.7488).