Energy Projects Near You

Stanton solar park (5 MW)

Stanton solar park is a 5 MW solar farm project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2015; the record was last updated on 2 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
2 August 2016record last updated
Swindoncouncil area

Planning timeline

DateStage
7 May 2014Application submitted
19 August 2014Planning permission granted
28 January 2015Construction started
15 March 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
2 August 2016
Operator or applicant
Quercus Renewable Holding 2
Planning authority
Swindon
Planning application reference
S/14/0757
Site area
13.2 ha
Address (REPD)
Land At Trenchard Road Stanton Fitzwarren Swindon
Council area (by location)
Swindon
Time to decision
15 weeks
REPD reference
2062

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Corner Copse Solar Farmsolar farm49.9under construction1.0
Catsbrain Farmbattery storage30approved, not built1.9
Queenslaine Farm, Highworth Roadbattery storage66approved, not built2.0
Little Rose Lane, Blunsdonsolar farm15approved, not built3.2
Honda wind Farmwind farm6.9refused3.5
Sevor Farmsolar farm9.3operational3.8
Pentylands Farmsolar farm19operational4.1
Roves Farm (Solar)solar farm12.7operational4.3
Castle Eaton Farmsolar farm17.8operational4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6183, -1.7514).