Castle Eaton Farm (17.8 MW solar farm)

Castle Eaton Farm is a 17.8 MW solar farm project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2014; the record was last updated on 2 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.8 MWsolar farm
operationalstatus in REPD
2 September 2014record last updated
Swindoncouncil area

Planning timeline

DateStage
11 December 2012Application submitted
25 March 2013Planning permission granted
30 March 2014Operational

Project details

Technology
solar farm
Capacity
17.8 MW
Status (REPD)
operational
Record last updated
2 September 2014
Operator or applicant
Hive Energy
Planning authority
Swindon
Planning application reference
S/12/1766
Site area
40.3 ha
Address (REPD)
Mill Lane, Castle Eaton, Swindon
Council area (by location)
Swindon
Time to decision
15 weeks
REPD reference
1945

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Water Eaton Farm / Port Farmsolar farm34.8operational2.0
Little Rose Lane, Blunsdonsolar farm15approved, not built2.8
Pentylands Farmsolar farm19operational4.2
Stanton solar parksolar farm5operational4.4
Chapel Farmsolar farm5operational4.4
Corner Copse Solar Farmsolar farm49.9under construction5.3
Catsbrain Farmbattery storage30approved, not built6.1
Malmesbury Road Solar Farmsolar farm13approved, not built6.2
Queenslaine Farm, Highworth Roadbattery storage66approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6491, -1.7907).