Energy Projects Near You

Queenslaine Farm, Highworth Road (66 MW battery storage)

Queenslaine Farm, Highworth Road is a 66 MW battery storage project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 September 2025, not yet built; the record was last updated on 26 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

66 MWbattery storage
approved, not builtstatus in REPD
26 January 2026record last updated
Swindoncouncil area

Planning timeline

DateStage
6 March 2025Application submitted
12 September 2025Planning permission granted
12 September 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
66 MW
Status (REPD)
approved, not built
Record last updated
26 January 2026
Operator or applicant
Elgin Energy
Planning authority
Swindon
Planning application reference
S/25/0250
Address (REPD)
E/O A361 Highworth Road, Queenslaine Farm, Highworth, Swindon
Council area (by location)
Swindon
Time to decision
27 weeks
Name in REPD
Queenslaine Farm, Highworth Road - Battery Energy Storage System
REPD reference
18424

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Corner Copse Solar Farmsolar farm49.9under construction1.1
Catsbrain Farmbattery storage30approved, not built1.3
Sevor Farmsolar farm9.3operational1.8
Honda wind Farmwind farm6.9refused1.9
Stanton solar parksolar farm5operational2.0
Roves Farm (Solar)solar farm12.7operational2.5
Westmill Wind Farmwind farm6.5operational4.7
Little Rose Lane, Blunsdonsolar farm15approved, not built5.0
Pentylands Farmsolar farm19operational5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6053, -1.7318).