Corner Copse Solar Farm (49.9 MW)

Corner Copse Solar Farm is a 49.9 MW solar farm project in Swindon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 28 April 2024; the record was last updated on 12 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
under constructionstatus in REPD
12 May 2025record last updated
Swindoncouncil area

Planning timeline

DateStage
31 July 2019Application submitted
25 June 2020Planning permission granted
28 April 2024Construction started

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
12 May 2025
Operator or applicant
BayWa r.e. UK Limited
Planning authority
Swindon
Planning application reference
S/19/1097
Site area
95.5 ha
Address (REPD)
Corner Copse Solar Farm, Stanton Fitzwarren, Swindon,
Council area (by location)
Swindon
Time to decision
47 weeks
Contracts for Difference
AR4
REPD reference
7519

Who decides

ApplicationsSwindonUK
Decided applications (solar, wind, battery)4310,236
Refused1 (2%)19%
Solar refused0 of 3512%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stanton solar parksolar farm5operational1.0
Queenslaine Farm, Highworth Roadbattery storage66approved, not built1.1
Catsbrain Farmbattery storage30approved, not built1.7
Sevor Farmsolar farm9.3operational2.9
Honda wind Farmwind farm6.9refused2.9
Roves Farm (Solar)solar farm12.7operational3.3
Little Rose Lane, Blunsdonsolar farm15approved, not built4.3
Pentylands Farmsolar farm19operational4.3
Westmill Wind Farmwind farm6.5operational4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6148, -1.7376).