Energy Projects Near You

Water Eaton Farm / Port Farm (34.8 MW solar farm)

Water Eaton Farm / Port Farm is a 34.8 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 March 2015; the record was last updated on 2 March 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34.8 MWsolar farm
operationalstatus in REPD
2 March 2018record last updated
Wiltshirecouncil area

Planning timeline

DateStage
25 April 2014Application submitted
21 August 2014Planning permission granted
1 October 2014Construction started
25 March 2015Operational

Project details

Technology
solar farm
Capacity
34.8 MW
Status (REPD)
operational
Record last updated
2 March 2018
Operator or applicant
Foresight/ Vogt solar
Planning authority
Wiltshire
Planning application reference
14/04326/FUL
Site area
60.8 ha
Address (REPD)
Land at Water Eaton Farm, Latton
Council area (by location)
Wiltshire
Time to decision
17 weeks
REPD reference
2085

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Castle Eaton Farmsolar farm17.8operational2.0
Little Rose Lane, Blunsdonsolar farm15approved, not built2.6
Chapel Farmsolar farm5operational3.4
Malmesbury Road Solar Farmsolar farm13approved, not built4.2
Stanton solar parksolar farm5operational5.4
Bentham House Farm, Mopes Lane Solar Farmsolar farm12approved, not built5.8
Pentylands Farmsolar farm19operational6.1
Corner Copse Solar Farmsolar farm49.9under construction6.4
Mopes Lane, Purton Solar Farmsolar farm20approved, not built6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6433, -1.8178).