Energy Projects Near You

Solar, wind and battery projects near Cirencester (GL7)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL7 (Cotswold): 4 are waiting for a planning decision, 6 approved but not yet running, 6 operational. The largest live scheme is Spratsgate Lane, Siddington Solar Farm and Battery Energy Storage System (25 MW solar farm, application submitted on 12 June 2025, no decision recorded), 6.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
4awaiting a decision
6approved, not running
6operational

Projects within 10 km of GL7

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cirencester Solar Farmsolar farmsolar farm23operationalupdated Jan 2020May 2015granted Sep 2015Jan 2020Cotswold1.7
Cirencester Solar Farmbattery storagebattery storage10operationalupdated Dec 2022May 2015granted Sep 2015Dec 2022Cotswold1.7
Crucis Parksolar farmsolar farm12.5operationalupdated Oct 2014Aug 2013granted Dec 2013Oct 2014Cotswold1.8
Duke Of Gloucester Barrackssolar farmsolar farm1.4operationalupdated Jan 2022Nov 2019granted May 2020Jan 2022Cotswold3.1
Siddington Solar Farmsolar farmsolar farm19.9under constructionupdated Jul 2023Dec 2020granted May 2021Jul 2023Cotswold4.5
Welsh Way Solar PV Farmsolar farmsolar farm13approved, not builtupdated Apr 2026Dec 2023granted Sep 2024Apr 2026Cotswold5.5
Spratsgate Lane, Siddington Solar Farm and Battery Energy Storage Systemsolar farmsolar farm25application submittedupdated Aug 2025Jun 2025—Aug 2025Cotswold6.2
Malmesbury Road Solar Farmsolar farmsolar farm13approved, not builtupdated Mar 2022Sep 2021granted Oct 2023Mar 2022Wiltshire8.1
Land At Sandpool Farmsolar farmsolar farm1application withdrawnupdated Jul 2013Jan 2013—Jul 2013Cotswold9.3
Water Eaton Farm / Port Farmsolar farmsolar farm34.8operationalupdated Mar 2018Apr 2014granted Aug 2014Mar 2018Wiltshire9.3
Chelworth Industrial Estate Solar Parksolar farmsolar farm1operationalupdated Nov 2014Dec 2012granted Apr 2013Nov 2014Wiltshire9.3
Cooles Farm, Minety Solar Park/Battery Storagesolar farmsolar farm8application submitted may be out of dateupdated Dec 2022Nov 2022—Dec 2022Wiltshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cotswold District Council, Trinity Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Dec 2023granted Jan 2024Jan 2024Cotswold4.8
Cotswold Leisure Centre, Old Tetbury Roadrooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Cotswold5.4
Spratsgate Lane, Siddington Solar Farm and Battery Energy Storage Systembattery storagebattery storage—application submittedupdated Aug 2025Jun 2025—Aug 2025Cotswold6.2
Chelworth Park, Chelworth Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2024Apr 2024granted Jun 2024Jun 2024Wiltshire9.0
Cooles Farm, Minety Solar Park/Battery Storagebattery storagebattery storage—application submitted may be out of dateupdated Dec 2022Nov 2022—Dec 2022Wiltshire10.0

Distance from the average position of the GL7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm11235078.9
Rooftop solar303000.8
Battery storage320100

MW in pipeline: pending, approved and under-construction capacity.

How Cotswold decides solar, wind and battery applications

ApplicationsCotswoldUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused2 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in Cotswold

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL7, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.