Energy Projects Near You

Spratsgate Lane, Siddington Solar Farm and Battery Energy Storage System (25 MW)

Spratsgate Lane, Siddington Solar Farm and Battery Energy Storage System is a 25 MW solar farm project in Cotswold, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 12 June 2025, no decision recorded; the record was last updated on 11 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
application submittedstatus in REPD
11 August 2025record last updated
Cotswoldcouncil area

Planning timeline

DateStage
12 June 2025Application submitted

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
application submitted
Record last updated
11 August 2025
Operator or applicant
Aura Power Developments Limited
Planning authority
Cotswold
Planning application reference
25/01623/FUL
Site area
52.0 ha
Address (REPD)
Spratsgate Lane Siddington
Council area (by location)
Cotswold
Name in REPD
Spratsgate Lane, Siddington - Solar Farm and Battery Energy Storage System
REPD reference
19220

The scheme also includes battery storage, recorded separately in REPD (application submitted).

Who decides

ApplicationsCotswoldUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused2 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Siddington Solar Farmsolar farm19.9under construction1.8
Cirencester Solar Farmsolar farm23operational4.6
Kemble Wicksolar farm49.9operational4.7
Cooles Farm, Minety Solar Park/Battery Storagesolar farm8application submitted5.8
Crucis Parksolar farm12.5operational6.0
Fairholme, Minetybattery storage50approved, not built8.6
Malmesbury Road Solar Farmsolar farm13approved, not built8.8
Minety South 2battery storage50operational9.0
National Grid Minety Substationbattery storage49.9approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.688, -1.978).