Energy Projects Near You

Cirencester Solar Farm (23 MW)

Cirencester Solar Farm is a 23 MW solar farm project in Cotswold, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 October 2022; the record was last updated on 24 January 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23 MWsolar farm
operationalstatus in REPD
24 January 2020record last updated
Cotswoldcouncil area

Planning timeline

DateStage
8 May 2015Application submitted
17 September 2015Planning permission granted
6 September 2018Construction started
13 October 2022Operational

Project details

Technology
solar farm
Capacity
23 MW
Status (REPD)
operational
Record last updated
24 January 2020
Operator or applicant
Warrington Borough Council / Statkraft
Planning authority
Cotswold
Planning application reference
15/01923/FUL
Site area
45.5 ha
Address (REPD)
Land Parcel East Of, Wilpit Lane, Preston, Cirencester
Council area (by location)
Cotswold
Time to decision
19 weeks
REPD reference
5276

The scheme also includes 10 MW of battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsCotswoldUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused2 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crucis Parksolar farm12.5operational1.6
Siddington Solar Farmsolar farm19.9under construction3.1
Spratsgate Lane, Siddington Solar Farm and Battery Energy Storage Systemsolar farm25application submitted4.6
Welsh Way Solar PV Farmsolar farm13approved, not built7.2
Malmesbury Road Solar Farmsolar farm13approved, not built8.5
Cooles Farm, Minety Solar Park/Battery Storagesolar farm8application submitted9.2
Kemble Wicksolar farm49.9operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7109, -1.9217).