Energy Projects Near You

Kemble Wick (49.9 MW solar farm)

Kemble Wick is a 49.9 MW solar farm project in Cotswold, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2026; the record was last updated on 14 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
operationalstatus in REPD
14 April 2026record last updated
Cotswoldcouncil area

Planning timeline

DateStage
27 July 2021Application submitted
25 March 2022Planning permission granted
1 February 2025Construction started
1 February 2026Operational

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
14 April 2026
Operator or applicant
Aura Power
Planning authority
Cotswold
Planning application reference
PL/2021/06919
Site area
19.8 ha
Address (REPD)
Kemble Wick, Cirencester,
Council area (by location)
Cotswold
Time to decision
34 weeks
Contracts for Difference
AR5
REPD reference
8136

Who decides

ApplicationsCotswoldUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused2 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cooles Farm, Minety Solar Park/Battery Storagesolar farm8application submitted4.7
Spratsgate Lane, Siddington Solar Farm and Battery Energy Storage Systemsolar farm25application submitted4.7
Lodge Farm (Poulshot)solar farm14.5operational5.0
Stonehill Energy Storagebattery storage50approved, not built6.2
Minety South 2battery storage50operational6.2
Siddington Solar Farmsolar farm19.9under construction6.3
National Grid Minety Substationbattery storage49.9approved, not built6.3
Stonehill Energy Storage / Upper Minetybattery storage50operational6.4
Stonehill Energy Storage / Upper Minetybattery storage50operational6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6603, -2.0303).