Lodge Farm (Poulshot) (14.5 MW solar farm)

Lodge Farm (Poulshot) is a 14.5 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 15 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.5 MWsolar farm
operationalstatus in REPD
15 April 2015record last updated
Wiltshirecouncil area

Planning timeline

DateStage
23 October 2013Application submitted
27 February 2014Planning permission granted
15 September 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
14.5 MW
Status (REPD)
operational
Record last updated
15 April 2015
Operator or applicant
Hive Energy
Planning authority
Wiltshire
Planning application reference
13/05244/FUL
Site area
32.2 ha
Address (REPD)
Lodge Farm Poulshot Road Poulshot Devizes Wiltshire
Council area (by location)
Wiltshire
Time to decision
18 weeks
REPD reference
2351

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crudwell Road Solar Farm & Battery Storagesolar farm49.9approved, not built3.1
Stonehill Energy Storagebattery storage50approved, not built3.5
Minety Substationsolar farm40approved, not built3.6
Stonehill Energy Storage / Upper Minetybattery storage50operational3.7
Stonehill Energy Storage / Lower Minetybattery storage50operational3.7
Stonehill Energy Storage / Upper Minetybattery storage50operational3.7
Malmesbury Solarsolar farm5operational3.9
National Grid Minety Substationbattery storage49.9approved, not built3.9
Minety South 2battery storage50operational4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6176, -2.0531).