Malmesbury Solar (5 MW)

Malmesbury Solar is a 5 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 July 2011; the record was last updated on 6 March 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
6 March 2013record last updated
Wiltshirecouncil area

Planning timeline

DateStage
25 March 2011Application submitted
26 May 2011Planning permission granted
25 July 2011Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
6 March 2013
Operator or applicant
Sunstroom Energy
Planning authority
Wiltshire
Planning application reference
11/01081/FUL
Site area
14.2 ha
Address (REPD)
Upper Marsh Farm, Brokenborough, Malmesbury
Council area (by location)
Wiltshire
Time to decision
9 weeks
REPD reference
1079

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Marsh Farmsolar farm14operational0.3
Newnton Dairy Farmsolar farm7.2operational0.4
Crudwell Road Solar Farm & Battery Storagesolar farm49.9approved, not built1.8
Lodge Farm (Poulshot)solar farm14.5operational3.9
Kemble Wicksolar farm49.9operational6.7
Rodbourne Rail Farm Solar Parksolar farm7.6operational7.1
Stonehill Energy Storagebattery storage50approved, not built7.4
Minety Substationsolar farm40approved, not built7.5
Stonehill Energy Storage / Upper Minetybattery storage50operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6243, -2.1089).