Crudwell Road Solar Farm & Battery Storage (49.9 MW)

Crudwell Road Solar Farm & Battery Storage is a 49.9 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 August 2023, not yet built; the record was last updated on 17 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
17 February 2026record last updated
Wiltshirecouncil area

Planning timeline

DateStage
25 March 2021Application submitted
23 August 2023Planning permission granted
22 August 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
17 February 2026
Operator or applicant
Five Lanes Solar Limited
Planning authority
Wiltshire
Planning application reference
20/08618/FUL
Site area
63.3 ha
Address (REPD)
Land west of A429 (Crudwell Road) North of Malmesbury
Council area (by location)
Wiltshire
Time to decision
126 weeks
Contracts for Difference
AR7a
REPD reference
8918

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Malmesbury Solarsolar farm5operational1.8
Marsh Farmsolar farm14operational2.1
Newnton Dairy Farmsolar farm7.2operational2.1
Lodge Farm (Poulshot)solar farm14.5operational3.1
Rodbourne Rail Farm Solar Parksolar farm7.6operational5.5
Minety Substationsolar farm40approved, not built6.2
Stonehill Energy Storagebattery storage50approved, not built6.2
Stonehill Energy Storage / Lower Minetybattery storage50operational6.4
Stonehill Energy Storage / Upper Minetybattery storage50operational6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6103, -2.0961).