Energy Projects Near You

Crucis Park (12.5 MW solar farm)

Crucis Park is a 12.5 MW solar farm project in Cotswold, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 July 2014; the record was last updated on 2 October 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWsolar farm
operationalstatus in REPD
2 October 2014record last updated
Cotswoldcouncil area

Planning timeline

DateStage
22 August 2013Application submitted
20 December 2013Planning permission granted
1 March 2014Construction started
31 July 2014Operational

Project details

Technology
solar farm
Capacity
12.5 MW
Status (REPD)
operational
Record last updated
2 October 2014
Operator or applicant
Solar Planning Limited
Planning authority
Cotswold
Planning application reference
13/03656/FUL
Site area
34.0 ha
Address (REPD)
Crucis Park, Barnsley Road, Ampney Crucis, Cirencester, Gloucestershire, GL7 5DX
Council area (by location)
Cotswold
Time to decision
17 weeks
REPD reference
2136

Who decides

ApplicationsCotswoldUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused2 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cirencester Solar Farmsolar farm23operational1.6
Siddington Solar Farmsolar farm19.9under construction4.6
Spratsgate Lane, Siddington Solar Farm and Battery Energy Storage Systemsolar farm25application submitted6.0
Welsh Way Solar PV Farmsolar farm13approved, not built6.5
Malmesbury Road Solar Farmsolar farm13approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7241, -1.9132).