Blenches Mill (6.1 MW solar farm)

Blenches Mill is a 6.1 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 26 July 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.1 MWsolar farm
operationalstatus in REPD
26 July 2018record last updated
Wiltshirecouncil area

Planning timeline

DateStage
22 November 2012Application submitted
28 November 2013Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
6.1 MW
Status (REPD)
operational
Record last updated
26 July 2018
Operator or applicant
NextEnery Solar Fund (NESF)
Planning authority
Wiltshire
Planning application reference
W/12/02081/FUL
Address (REPD)
Adj Sewage Treatment Works, Slag Lane, Westbury, Wiltshire
Council area (by location)
Wiltshire
Time to decision
53 weeks
REPD reference
1969

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Storridge Road Solar Farmsolar farm31approved, not built2.0
Land West Side of Axe and Cleaver Lanesolar farm5operational2.5
Land at Poles Hole Farmsolar farm6.8operational3.4
Hoopers Pool, Southwicksolar farm30application submitted4.4
Bluebell Wood Solar Farm & Battery Storagesolar farm49.9approved, not built5.0
Trowle Commonsolar farm5operational6.5
Cockhill Solar Farmsolar farm20operational6.8
Lodge Hill, Berkley Solar Parksolar farm14.5approved, not built7.1
St Georges Cross Farm, Berkley Lanebattery storage60refused7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2746, -2.1899).