Bluebell Wood Solar Farm & Battery Storage (49.9 MW)

Bluebell Wood Solar Farm & Battery Storage is a 49.9 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 July 2024, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
Somersetcouncil area

Planning timeline

DateStage
13 November 2023Application submitted
16 July 2024Planning permission granted
16 July 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Low Carbon UK Solar Investment Co Limited
Planning authority
Somerset
Planning application reference
2023/2183/FUL
Site area
74.3 ha
Address (REPD)
S/O Flexham Farm, Bradford Road, Rode, Frome
Council area (by location)
Somerset
Time to decision
35 weeks
Contracts for Difference
AR7a
REPD reference
13988

The scheme also includes 50 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hoopers Pool, Southwicksolar farm30application submitted1.0
Land at Poles Hole Farmsolar farm6.8operational2.1
Storridge Road Solar Farmsolar farm31approved, not built3.3
Land West Side of Axe and Cleaver Lanesolar farm5operational3.5
St Georges Cross Farm, Berkley Lanebattery storage60refused4.1
Trowle Commonsolar farm5operational5.0
Blenches Millsolar farm6.1operational5.0
Lodge Hill, Berkley Solar Parksolar farm14.5approved, not built5.7
Cockhill Solar Farmsolar farm20operational5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.285, -2.2603).