Energy Projects Near You

St Georges Cross Farm, Berkley Lane (60 MW battery storage)

St Georges Cross Farm, Berkley Lane is a 60 MW battery storage project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 17 April 2026; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWbattery storage
refusedstatus in REPD
19 May 2026record last updated
Somersetcouncil area

Planning timeline

DateStage
30 April 2025Application submitted
17 April 2026Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
60 MW
Status (REPD)
refused
Record last updated
19 May 2026
Operator or applicant
Integrum SPV 23101 Limited
Planning authority
Somerset
Planning application reference
2025/0690/FUL
Address (REPD)
St Georges Cross Farm, Berkley Lane, Berkley, Frome
Council area (by location)
Somerset
Time to decision
50 weeks
Name in REPD
St Georges Cross Farm, Berkley Lane - Battery Energy Storage
REPD reference
18878

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lodge Hill, Berkley Solar Parksolar farm14.5approved, not built2.6
Frome Power, Styles Close Energy Storage Facilitybattery storage30application submitted2.7
Bluebell Wood Solar Farm & Battery Storagesolar farm49.9approved, not built4.1
Selwood Solar Farmsolar farm6application withdrawn4.3
Hoopers Pool, Southwicksolar farm30application submitted5.0
Storridge Road Solar Farmsolar farm31approved, not built5.3
Land at Poles Hole Farmsolar farm6.8operational5.8
Little Sharpshaw Farm solar parksolar farm5.3refused6.6
Court Farm (Frome)solar farm6.8refused on appeal6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2529, -2.29).