Energy Projects Near You

Rudge Farm Solar Farm (7 MW)

Rudge Farm Solar Farm is a 7 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2013; the record was last updated on 10 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
10 May 2016record last updated
Wiltshirecouncil area

Planning timeline

DateStage
26 July 2012Application submitted
21 December 2012Planning permission granted
22 December 2012Construction started
28 March 2013Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
10 May 2016
Operator or applicant
Orta Solar
Planning authority
Wiltshire
Planning application reference
E/2012/0946/FUL
Site area
18.9 ha
Address (REPD)
Rudge Manor Farm, Rudge, Marlborough
Council area (by location)
Wiltshire
Time to decision
21 weeks
Name in REPD
RUDGE FARM SOLAR FARM
REPD reference
1091

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hadley Farm (Orta Membury Solar Farm)solar farm17operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4204, -1.6067).