Energy Projects Near You

Monksham Solar Farm (10.7 MW)

Monksham Solar Farm is a 10.7 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2014; the record was last updated on 13 August 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.7 MWsolar farm
operationalstatus in REPD
13 August 2015record last updated
Somersetcouncil area

Planning timeline

DateStage
16 May 2013Application submitted
17 September 2013Planning permission granted
30 March 2014Operational

Project details

Technology
solar farm
Capacity
10.7 MW
Status (REPD)
operational
Record last updated
13 August 2015
Operator or applicant
John Laing Environmental Assets Group
Planning authority
Somerset
Planning application reference
2013/1118
Address (REPD)
Monksham Farm, Marston Bigot, Frome
Council area (by location)
Somerset
Time to decision
18 weeks
REPD reference
2039

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Court Farm (Frome)solar farm6.8refused on appeal1.7
West Woodlandssolar farm5operational1.7
Little Sharpshaw Farm solar parksolar farm5.3refused2.8
Holwell Hillsolar farm6operational3.7
Selwood Solar Farmsolar farm6application withdrawn4.0
Frome Power, Styles Close Energy Storage Facilitybattery storage30application submitted5.6
Lodge Hill, Berkley Solar Parksolar farm14.5approved, not built7.2
St Georges Cross Farm, Berkley Lanebattery storage60refused8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1846, -2.3358).