Somerton Door Farm (8.7 MW solar farm)

Somerton Door Farm is an 8.7 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.7 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
Somersetcouncil area

Planning timeline

DateStage
5 March 2014Application submitted
2 June 2014Planning permission granted
18 August 2014Construction started
1 March 2015Operational

Project details

Technology
solar farm
Capacity
8.7 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Somerset
Planning application reference
14/00876/FUL
Site area
18.2 ha
Address (REPD)
Land At Somerton Door Farm, Somerton Door Drove, Somerton, Somerset
Council area (by location)
Somerset
Time to decision
13 weeks
REPD reference
1836

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Somerton Door Farm, Somerton Door Drove Solar farmsolar farm20application submitted<0.1
Little Park Farmsolar farm8.6application withdrawn0.8
Higher Hill Farmsolar farm5operational4.9
Redlands Farmsolar farm6.2operational6.7
Nythe Road, Pedwell Solar Photovoltaic Parksolar farm40application submitted6.9
Park Wood Solar Farmsolar farm5operational7.2
Aller Court Farm Solar Parksolar farm5operational7.6
Tintinhull Forts Solar Parksolar farm6refused8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0673, -2.7573).