Energy Projects Near You

Redlands Farm (6.2 MW solar farm)

Redlands Farm is a 6.2 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 February 2015; the record was last updated on 16 June 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWsolar farm
operationalstatus in REPD
16 June 2015record last updated
Somersetcouncil area

Planning timeline

DateStage
20 June 2013Application submitted
11 November 2013Planning permission granted
1 September 2014Construction started
18 February 2015Operational

Project details

Technology
solar farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
16 June 2015
Operator or applicant
juwi Renewable Energies
Planning authority
Somerset
Planning application reference
2013/1189
Address (REPD)
N/O Butleigh Drove,, Butleigh Drove, Pedwell, Bridgwater, Somerset
Council area (by location)
Somerset
Time to decision
21 weeks
REPD reference
1764

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nythe Road, Pedwell Solar Photovoltaic Parksolar farm40application submitted0.3
Little Park Farmsolar farm8.6application withdrawn6.1
Somerton Door Farm, Somerton Door Drove Solar farmsolar farm20application submitted6.6
Somerton Door Farmsolar farm8.7operational6.7
Aller Court Farm Solar Parksolar farm5operational6.9
Higher Hill Farmsolar farm5operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1129, -2.8192).