Energy Projects Near You

Aller Court Farm Solar Park (5 MW)

Aller Court Farm Solar Park is a 5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2017; the record was last updated on 3 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
3 May 2017record last updated
Somersetcouncil area

Planning timeline

DateStage
22 September 2014Application submitted
23 July 2015Refused by the planning authority
10 November 2015Appeal lodged
8 June 2016Planning permission granted
8 June 2016Appeal allowed
1 February 2017Construction started
1 April 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
3 May 2017
Operator or applicant
NESF (formerly British Solar Renewables)
Planning authority
Somerset
Planning application reference
14/04300/FUL
Appeal reference
APP/R3325/W/15/3135346
Site area
13.5 ha
Address (REPD)
Land Os 4716 And Os 4300, Church Path, Aller, Langport, Somerset
Council area (by location)
Somerset
Time to decision
89 weeks
REPD reference
1646

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Little Park Farmsolar farm8.6application withdrawn6.8
Redlands Farmsolar farm6.2operational6.9
Nythe Road, Pedwell Solar Photovoltaic Parksolar farm40application submitted7.3
Somerton Door Farmsolar farm8.7operational7.6
Somerton Door Farm, Somerton Door Drove Solar farmsolar farm20application submitted7.6
Bushfurlong Solar Farmsolar farm5application withdrawn7.8
Langport Farmsolar farm5application withdrawn8.0
North Newton Solar Farmsolar farm30application submitted9.6
Impens Farm Solar Farm & Battery Storagesolar farm49.9approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0576, -2.8652).