Stoneyard Lane Wind Farm (10 MW)

Stoneyard Lane Wind Farm is a 10 MW wind farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 24 January 2012; the record was last updated on 30 January 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
refused on appealstatus in REPD
30 January 2012record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
10 September 2010Application submitted
18 March 2011Refused by the planning authority
24 January 2012Appeal refused

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
refused on appeal
Record last updated
30 January 2012
Operator or applicant
Wind Prospect
Planning authority
South Gloucestershire
Planning application reference
not recorded
Turbines
4
Address (REPD)
near Oldbury on Severn, South Gloucestershire,
Council area (by location)
South Gloucestershire
Time to decision
27 weeks
REPD reference
2759

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill Court Solar farm & Battery storagebattery storage35approved, not built1.8
Hill Court, Tranton Lane Hill Solar Farmsolar farm49.9approved, not built1.8
Worlds End Solar Farmsolar farm49.9application submitted3.3
Woodlands Farm, Clapton - Ground Mounted Solar Parksolar farm36approved, not built4.5
Tower Hill Farmsolar farm8.1operational6.8
Hook Street Energy Storage Compoundbattery storage100refused7.0
Watts Group Factory Sitebattery storage10abandoned7.5
Varley , Talbot End Farm, Cromhall Solar Farmsolar farm25approved, not built7.5
Land North of Actrees Solar Farmbattery storage49.9abandoned8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6479, -2.5286).