Tower Hill Farm (8.1 MW solar farm)

Tower Hill Farm is an 8.1 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 1 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.1 MWsolar farm
operationalstatus in REPD
1 December 2015record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
16 July 2014Application submitted
15 October 2014Planning permission granted
1 January 2015Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
8.1 MW
Status (REPD)
operational
Record last updated
1 December 2015
Operator or applicant
NextEnergy Solar Fund (NESF)
Planning authority
South Gloucestershire
Planning application reference
PT14/2810/F
Site area
25.4 ha
Address (REPD)
Land At Cuttsheath Road And New Road, Tytherington, Wotton Under Edge, South Gloucestershire
Council area (by location)
South Gloucestershire
Time to decision
13 weeks
REPD reference
2077

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Larks Green Solar Farmsolar farm70operational2.2
Larks Lane, Iron Actonbattery storage20application submitted3.1
Varley , Talbot End Farm, Cromhall Solar Farmsolar farm25approved, not built3.1
Patch Elm Lanebattery storage35approved, not built3.2
Lower Larks Farmbattery storage99.9approved, not built3.2
Rag Lane Solar Farmsolar farm49.9approved, not built3.3
Alveston Wind Parkwind farm6.9operational3.4
Iron Acton Substation, Latteridge Lanebattery storage99approved, not built3.4
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built3.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5973, -2.4724).