Hook Street Energy Storage Compound (100 MW)
Hook Street Energy Storage Compound is a 100 MW battery storage project in Stroud, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 29 June 2023; the record was last updated on 19 January 2022.
100 MWbattery storage
refusedstatus in REPD
19 January 2022record last updated
Stroudcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 December 2021 | Application submitted |
| 29 June 2023 | Refused by the planning authority |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 100 MW
- Status (REPD)
- refused
- Record last updated
- 19 January 2022
- Operator or applicant
- Immersa
- Planning authority
- Stroud
- Planning application reference
- S.21/3064/FUL
- Address (REPD)
- Sanigar Farm, Hook Street, Berkeley
- Council area (by location)
- Stroud
- Time to decision
- 79 weeks
- Name in REPD
- Hook Street - Energy Storage Compound
- REPD reference
- 10142
Who decides
| Applications | Stroud | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 34 | 10,236 |
| Refused | 8 (24%) | 19% |
| Solar refused | 4 of 25 | 12% |
| Onshore wind refused | 3 of 4 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 17.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Woodlands Farm, Clapton - Ground Mounted Solar Park | solar farm | 36 | approved, not built | 2.5 |
| Land North of Actrees Solar Farm | battery storage | 49.9 | abandoned | 3.6 |
| Land At Actrees Farm | solar farm | 5 | operational | 3.8 |
| Worlds End Solar Farm | solar farm | 49.9 | application submitted | 3.8 |
| Berkeley Vale | wind farm | 16 | refused | 4.2 |
| Hurst Farm | solar farm | 5 | operational | 4.4 |
| Watts Group Factory Site | battery storage | 10 | abandoned | 5.0 |
| Upper Wick Solar Farm | solar farm | 5 | operational | 5.4 |
| Nibley Mill Farm | solar farm | 15.9 | refused | 5.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6983, -2.467).