Upper Wick Solar Farm (5 MW)

Upper Wick Solar Farm is a 5 MW solar farm project in Stroud, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 January 2016; the record was last updated on 21 April 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
21 April 2020record last updated
Stroudcouncil area

Planning timeline

DateStage
7 November 2014Application submitted
14 January 2015Planning permission granted
16 September 2015Construction started
18 January 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
21 April 2020
Operator or applicant
Upper Wick Solar Farm
Planning authority
Stroud
Planning application reference
S.14/2460/FUL
Site area
13.2 ha
Address (REPD)
Land Parcel To East of Wick Bridge, Upper Wick, Dursley
Council area (by location)
Stroud
Time to decision
10 weeks
REPD reference
4751

Who decides

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Actrees Farmsolar farm5operational1.8
Land North of Actrees Solar Farmbattery storage49.9abandoned1.9
Upper Huntingford Farmsolar farm7.7operational2.6
Berkeley Valewind farm16refused2.6
Hook Street Energy Storage Compoundbattery storage100refused5.4
Woodlands Farm, Clapton - Ground Mounted Solar Parksolar farm36approved, not built5.7
Varley , Talbot End Farm, Cromhall Solar Farmsolar farm25approved, not built6.3
Worlds End Solar Farmsolar farm49.9application submitted6.9
Kingston Road, Slimbridgebattery storage36approved, not built7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6668, -2.4082).