Upper Huntingford Farm (7.7 MW solar farm)
Upper Huntingford Farm is a 7.7 MW solar farm project in Stroud, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 January 2016; the record was last updated on 4 September 2018.
7.7 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Stroudcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 15 April 2014 | Application submitted |
| 14 July 2014 | Planning permission granted |
| 28 June 2015 | Construction started |
| 16 January 2016 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 7.7 MW
- Status (REPD)
- operational
- Record last updated
- 4 September 2018
- Operator or applicant
- Foresight
- Planning authority
- Stroud
- Planning application reference
- S.14/0929/FUL
- Site area
- 12.9 ha
- Address (REPD)
- Upper Huntingford Farm Charfield, Wotton-Under-Edge, Gloucestershire, GL12 8EY
- Council area (by location)
- Stroud
- Time to decision
- 13 weeks
- REPD reference
- 2083
Who decides
| Applications | Stroud | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 34 | 10,236 |
| Refused | 8 (24%) | 19% |
| Solar refused | 4 of 25 | 12% |
| Onshore wind refused | 3 of 4 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 17.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Upper Wick Solar Farm | solar farm | 5 | operational | 2.6 |
| Varley , Talbot End Farm, Cromhall Solar Farm | solar farm | 25 | approved, not built | 4.0 |
| Land At Actrees Farm | solar farm | 5 | operational | 4.3 |
| Land North of Actrees Solar Farm | battery storage | 49.9 | abandoned | 4.4 |
| Berkeley Vale | wind farm | 16 | refused | 5.2 |
| Rag Lane Solar Farm | solar farm | 49.9 | approved, not built | 5.8 |
| Tower Hill Farm | solar farm | 8.1 | operational | 6.9 |
| Woodlands Farm, Clapton - Ground Mounted Solar Park | solar farm | 36 | approved, not built | 7.0 |
| Hook Street Energy Storage Compound | battery storage | 100 | refused | 7.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6436, -2.4065).