Energy Projects Near You

Solar, wind and battery projects near Dursley (GL11)

29 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL11 (Stroud): 1 is waiting for a planning decision, 13 approved but not yet running, 8 operational. The largest live scheme is Kingston Road, Slimbridge (36 MW battery storage, approved on 17 July 2024, not yet built), 5.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29projects within 10 km
1awaiting a decision
13approved, not running
8operational

Projects within 10 km of GL11

Projects of 1 MW and more (16)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land at Box Roadsolar farmsolar farm2.2operationalupdated Jun 2016Jun 2015granted Sep 2015Jun 2016Stroud3.1
Berkeley Valewind farmwind farm16refusedupdated Dec 2012Aug 2010refused Apr 2011Dec 2012Stroud3.5
Upper Wick Solar Farmsolar farmsolar farm5operationalupdated Apr 2020Nov 2014granted Jan 2015Apr 2020Stroud4.4
Land At Actrees Farmsolar farmsolar farm5operationalupdated Mar 2016Jun 2015granted Oct 2015Mar 2016Stroud4.4
Land North of Actrees Solar Farmbattery storagebattery storage49.9abandonedupdated Jan 2020Mar 2019—Jan 2020Stroud4.5
Hillhouse Farmsolar farmsolar farm28.5operationalupdated Apr 2015Aug 2014granted Dec 2014Apr 2015Stroud5.0
Kingston Road, Slimbridgebattery storagebattery storage36approved, not builtupdated Aug 2024Sep 2023granted Jul 2024Aug 2024Stroud5.4
Upper Huntingford Farmsolar farmsolar farm7.7operationalupdated Sep 2018Apr 2014granted Jul 2014Sep 2018Stroud6.2
Lynch Knoll Wind Farm (Extension)wind farmwind farm1.5appeal withdrawnupdated Jan 2010Oct 2000refused Dec 2000Jan 2010Stroud6.3
Fawkes 1solar farmsolar farm4.7refusedupdated Dec 2015Aug 2015refused Nov 2015Dec 2015Stroud6.4
Fawkes 2 Solar Farmsolar farmsolar farm4.7refusedupdated Dec 2015Jul 2015refused Nov 2015Dec 2015Stroud6.5
Windmill Hillwind farmwind farm1.5refusedupdated Feb 2004Oct 2000refused May 2001Feb 2004Stroud6.6
Hook Street Energy Storage Compoundbattery storagebattery storage100refusedupdated Jan 2022Dec 2021refused Jun 2023Jan 2022Stroud7.6
Delphi Diesel Systems, Brunel Wayrooftop solarrooftop solar1.6approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024Stroud7.8
Woodlands Farm, Clapton - Ground Mounted Solar Parksolar farmsolar farm36approved, not builtupdated Jun 2026Oct 2022granted Aug 2025Jun 2026Stroud9.1
Sharpness Dockswind turbinewind turbine2operationalupdated May 2018Dec 2011granted May 2014May 2018Stroud9.3
Smaller schemes under 1 MW, mostly rooftop solar (13)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rednock Schoolrooftop solarrooftop solar0.2under constructionupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Stroud0.4
Renishaw Plc, Old Townrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2022Apr 2022granted May 2022Apr 2022Stroud5.8
Building F, Renishaw Factoryrooftop solarrooftop solar0.2operationalupdated May 2020Nov 2018granted Mar 2022May 2020Stroud6.4
Brunel Wayrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Mar 2022Feb 2022granted Apr 2022Mar 2022Stroud7.7
A B B Limited, Oldends Lanesolar farmsolar farm0.8approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Stroud8.0
Renishaw PLC Factoryrooftop solarrooftop solar0.8operationalupdated May 2020Jun 2018granted Mar 2019May 2020Stroud8.1
Wellington House, Bath Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jan 2022Dec 2021Stroud9.1
Woodlands Farm, Clapton - Ground Mounted Solar Parkbattery storagebattery storage—approved, not builtupdated Jun 2026Oct 2022granted Aug 2025Jun 2026Stroud9.1
Shipton Mill Limited, Frampton On Severn Industrial Parkrooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024Stroud9.4
Sainsburys Supermarket, Dudbridge Roadrooftop solarrooftop solar0.2application submitted may be out of dateupdated Aug 2024Aug 2024—Aug 2024Stroud9.7
Gloucestershire Science And Technology Par Energy Storage Facilitybattery storagebattery storage—approved, not built may be out of dateupdated Mar 2022Feb 2022granted Oct 2022Mar 2022Stroud9.7
Eastwood Park, Falfield Solar Photovoltaic (PV) Panelssolar farmsolar farm0.2approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jul 2023Dec 2021South Gloucestershire9.8
Science building, Dudbridge Roadrooftop solarrooftop solar0.6approved, not builtupdated Apr 2023Feb 2023granted Mar 2023Apr 2023Stroud9.8

Distance from the average position of the GL11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm10035237
Rooftop solar1017203.8
Wind farm300020
Wind turbine100100
Battery storage5030136

MW in pipeline: pending, approved and under-construction capacity.

How Stroud decides solar, wind and battery applications

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Stroud

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL11, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.