Energy Projects Near You

Solar, wind and battery projects near Berkeley (GL13)

31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL13 (Stroud): 2 are waiting for a planning decision, 12 approved but not yet running, 10 operational. The largest live scheme is Worlds End Solar Farm (49.9 MW solar farm, application submitted on 11 May 2021, no decision recorded; REPD status may be out of date), 3.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

31projects within 10 km
2awaiting a decision
12approved, not running
10operational

Projects within 10 km of GL13

Projects of 1 MW and more (23)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hook Street Energy Storage Compoundbattery storagebattery storage100refusedupdated Jan 2022Dec 2021refused Jun 2023Jan 2022Stroud0.8
Woodlands Farm, Clapton - Ground Mounted Solar Parksolar farmsolar farm36approved, not builtupdated Jun 2026Oct 2022granted Aug 2025Jun 2026Stroud2.3
Land North of Actrees Solar Farmbattery storagebattery storage49.9abandonedupdated Jan 2020Mar 2019—Jan 2020Stroud3.0
Land At Actrees Farmsolar farmsolar farm5operationalupdated Mar 2016Jun 2015granted Oct 2015Mar 2016Stroud3.1
Berkeley Valewind farmwind farm16refusedupdated Dec 2012Aug 2010refused Apr 2011Dec 2012Stroud3.7
Sharpness Dockswind turbinewind turbine2operationalupdated May 2018Dec 2011granted May 2014May 2018Stroud3.7
Worlds End Solar Farmsolar farmsolar farm49.9application submitted may be out of dateupdated May 2021May 2021—May 2021Stroud3.7
Upper Wick Solar Farmsolar farmsolar farm5operationalupdated Apr 2020Nov 2014granted Jan 2015Apr 2020Stroud4.6
Hurst Farmsolar farmsolar farm5operationalupdated Nov 2014Sep 2013granted Nov 2013Nov 2014Forest of Dean5.2
Hill Court, Tranton Lane Hill Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Oct 2025Sep 2022granted Jun 2023Oct 2025South Gloucestershire5.6
Hill Court Solar farm & Battery storagebattery storagebattery storage35approved, not builtupdated Oct 2025Mar 2025granted May 2025Oct 2025South Gloucestershire5.6
Watts Group Factory Sitebattery storagebattery storage10abandonedupdated Sep 2019Apr 2017—Sep 2019Forest of Dean5.7
Nibley Mill Farmsolar farmsolar farm15.9refusedupdated Sep 2014May 2014refused Sep 2014Sep 2014Forest of Dean6.3
Upper Huntingford Farmsolar farmsolar farm7.7operationalupdated Sep 2018Apr 2014granted Jul 2014Sep 2018Stroud6.6
Stoneyard Lane Wind Farmwind farmwind farm10refused on appealupdated Jan 2012Sep 2010refused Mar 2011Jan 2012South Gloucestershire6.8
Kingston Road, Slimbridgebattery storagebattery storage36approved, not builtupdated Aug 2024Sep 2023granted Jul 2024Aug 2024Stroud7.2
Land at Box Roadsolar farmsolar farm2.2operationalupdated Jun 2016Jun 2015granted Sep 2015Jun 2016Stroud7.5
Solar Panels at Ne/O Poulton Court Farmsolar farmsolar farm40application submittedupdated Jun 2025May 2025—Jun 2025Forest of Dean7.7
Yorkley Solar Parksolar farmsolar farm5operationalupdated Jan 2016May 2015granted Jun 2015Jan 2016Forest of Dean7.9
Hillhouse Farmsolar farmsolar farm28.5operationalupdated Apr 2015Aug 2014granted Dec 2014Apr 2015Stroud8.3
Varley , Talbot End Farm, Cromhall Solar Farmsolar farmsolar farm25approved, not builtupdated Sep 2025Dec 2022granted Jan 2024Sep 2025South Gloucestershire9.0
Northington Lanebattery storagebattery storage35approved, not built may be out of dateupdated Nov 2021Nov 2021granted May 2023Nov 2021Forest of Dean9.5
Awre Penisular Farmer's Community Solar Schemesolar farmsolar farm49.9refusedupdated Dec 2017Jun 2015refused Jan 2016Dec 2017Forest of Dean9.6
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Woodlands Farm, Clapton - Ground Mounted Solar Parkbattery storagebattery storage—approved, not builtupdated Jun 2026Oct 2022granted Aug 2025Jun 2026Stroud2.3
Gloucestershire Science And Technology Par Energy Storage Facilitybattery storagebattery storage—approved, not built may be out of dateupdated Mar 2022Feb 2022granted Oct 2022Mar 2022Stroud2.6
Eastwood Park, Falfield Solar Photovoltaic (PV) Panelssolar farmsolar farm0.2approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jul 2023Dec 2021South Gloucestershire6.4
Jones Food Company Solar Farmrooftop solarrooftop solar0.7operationalupdated Feb 2024——Feb 2024Forest of Dean6.8
Rednock Schoolrooftop solarrooftop solar0.2under constructionupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Stroud7.2
Building F, Renishaw Factoryrooftop solarrooftop solar0.2operationalupdated May 2020Nov 2018granted Mar 2022May 2020Stroud8.4
Oldbury Power Station Solar Photo Voltaic Arrayrooftop solarrooftop solar0.1approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023South Gloucestershire9.0
Renishaw Plc, Old Townrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2022Apr 2022granted May 2022Apr 2022Stroud9.6

Distance from the average position of the GL13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm152472201
Rooftop solar503200.7
Wind farm200020
Wind turbine100100
Battery storage80501106

MW in pipeline: pending, approved and under-construction capacity.

How Stroud decides solar, wind and battery applications

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Stroud

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL13, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.