Energy Projects Near You

Renewable energy projects in Stroud

41 solar, wind or battery projects of 150 kW or more are located in Stroud (REPD, July 2026 extract): 2 pending, 17 approved but not running, 9 operational and 6 refused. The council refused 8 of 34 decided applications (24%; UK 19%), with a median 18 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41projects in the council area
2awaiting a decision
17approved, not running
24%of decisions refused

How Stroud decides

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Projects in Stroud

Projects of 1 MW and more (27)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Hook Street Energy Storage Compoundbattery storagebattery storage100refusedupdated Jan 2022Dec 2021refused Jun 2023Jan 2022
Land North of Actrees Solar Farmbattery storagebattery storage49.9abandonedupdated Jan 2020Mar 2019—Jan 2020
Solar PV Panels & Battery Storage Facilitysolar farmsolar farm49.9application withdrawnupdated Mar 2021Jun 2022—Mar 2021
Moreton Lane Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Feb 2021granted Apr 2022Apr 2022
Moreton Lane Solar Farm & Battery Storagebattery storagebattery storage49.9approved, not built may be out of dateupdated Apr 2022Feb 2021granted Apr 2022Apr 2022
Worlds End Solar Farmsolar farmsolar farm49.9application submitted may be out of dateupdated May 2021May 2021—May 2021
Solar PV Panels & Battery Storage Facilitybattery storagebattery storage49.9application withdrawnupdated Jul 2022Jun 2022—Jul 2022
Epney, Framilode Solar Farm & Battery Storagesolar farmsolar farm49.5refusedupdated Dec 2025Jun 2025refused Dec 2025Dec 2025
Woodlands Farm, Clapton - Ground Mounted Solar Parksolar farmsolar farm36approved, not builtupdated Jun 2026Oct 2022granted Aug 2025Jun 2026
Kingston Road, Slimbridgebattery storagebattery storage36approved, not builtupdated Aug 2024Sep 2023granted Jul 2024Aug 2024
Hillhouse Farmsolar farmsolar farm28.5operationalupdated Apr 2015Aug 2014granted Dec 2014Apr 2015
High Green Longney Estate Solar Farmsolar farmsolar farm25permission expiredupdated Sep 2020Mar 2018granted Sep 2019Sep 2020
High Green Longney Estate Solar Farmsolar farmsolar farm20permission expiredupdated Jul 2022Apr 2019granted Jul 2019Jul 2022
Berkeley Valewind farmwind farm16refusedupdated Dec 2012Aug 2010refused Apr 2011Dec 2012
Brookthorpe Solar Farmsolar farmsolar farm8approved, not builtupdated Feb 2026Apr 2024granted Dec 2024Feb 2026
Upper Huntingford Farmsolar farmsolar farm7.7operationalupdated Sep 2018Apr 2014granted Jul 2014Sep 2018
Upper Wick Solar Farmsolar farmsolar farm5operationalupdated Apr 2020Nov 2014granted Jan 2015Apr 2020
Land At Actrees Farmsolar farmsolar farm5operationalupdated Mar 2016Jun 2015granted Oct 2015Mar 2016
Fawkes 2 Solar Farmsolar farmsolar farm4.7refusedupdated Dec 2015Jul 2015refused Nov 2015Dec 2015
Fawkes 1solar farmsolar farm4.7refusedupdated Dec 2015Aug 2015refused Nov 2015Dec 2015
Land at Box Roadsolar farmsolar farm2.2operationalupdated Jun 2016Jun 2015granted Sep 2015Jun 2016
Sharpness Dockswind turbinewind turbine2operationalupdated May 2018Dec 2011granted May 2014May 2018
Delphi Diesel Systems, Brunel Wayrooftop solarrooftop solar1.6approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024
Windmill Hillwind farmwind farm1.5refusedupdated Feb 2004Oct 2000refused May 2001Feb 2004
Lynch Knoll Wind Farm (Extension)wind farmwind farm1.5appeal withdrawnupdated Jan 2010Oct 2000refused Dec 2000Jan 2010
Unit Q1, Quadrant Distribution Centre, Hardwickrooftop solarrooftop solar1approved, not builtupdated May 2022Apr 2022granted May 2022May 2022
Mounteneys and Cherry Rock Wind Turbineswind farmwind farm1operationalupdated May 2022Feb 2012—May 2022
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Renishaw PLC Factoryrooftop solarrooftop solar0.8operationalupdated May 2020Jun 2018granted Mar 2019May 2020
A B B Limited, Oldends Lanesolar farmsolar farm0.8approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024
Science building, Dudbridge Roadrooftop solarrooftop solar0.6approved, not builtupdated Apr 2023Feb 2023granted Mar 2023Apr 2023
Brunel Wayrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Mar 2022Feb 2022granted Apr 2022Mar 2022
MG Markey Group, Quadrant Wayrooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024
Renishaw Plc, Old Townrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2022Apr 2022granted May 2022Apr 2022
Wellington House, Bath Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jan 2022Dec 2021
Sainsburys Supermarket, Dudbridge Roadrooftop solarrooftop solar0.2application submitted may be out of dateupdated Aug 2024Aug 2024—Aug 2024
Rednock Schoolrooftop solarrooftop solar0.2under constructionupdated Sep 2024Jul 2024granted Sep 2024Sep 2024
Building F, Renishaw Factoryrooftop solarrooftop solar0.2operationalupdated May 2020Nov 2018granted Mar 2022May 2020
Dobbies Garden Centres, Bath Roadrooftop solarrooftop solar0.2application withdrawnupdated Dec 2023Oct 2023—Dec 2023
Shipton Mill Limited, Frampton On Severn Industrial Parkrooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024
Gloucestershire Science And Technology Par Energy Storage Facilitybattery storagebattery storage—approved, not built may be out of dateupdated Mar 2022Feb 2022granted Oct 2022Mar 2022
Woodlands Farm, Clapton - Ground Mounted Solar Parkbattery storagebattery storage—approved, not builtupdated Jun 2026Oct 2022granted Aug 2025Jun 2026

Postcode districts in Stroud

DistrictProjects within 10 kmPendingApprovedOperational
GL5211123
GL612151
GL10301164
GL11291138
GL12312159
GL133121210

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Stroud by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.